Forest Ridge Drive 12-Inch Water Line from Bedford Road to Harwood Road

Description: This is the eleventh project utilizing the State Water Implementation Fund for Texas (SWIFT) funding. The project would tie into the Harwood Road Water Line project, which is currently under construction to ensure adequate water supply to support the new infrastructure at Generations Park. This project includes 2,906 linear feet of 12-inch water line and 82 linear feet of 8-inch sanitary sewer line, plus related appurtenances (gate valve and boxes and any incidental work that may be needed).

Atkins Brothers Equipment Company Inc. (Atkins) submitted the lowest responsive bid of the eleven bids received on April 8, 2021. A pre-construction meeting with Atkins, staff, and the Project Engineer was held on September 23, 2021. 

After the completion of the waterline project, the City will follow up with pavement improvements on Forest Ridge Drive from Bedford Road to Harwood Road.

Project Cost: $746,403

Funding Source(s): 2015 Certificates of Obligation Bond, 2012A Certificates of Obligation Bond

Anticipated Completion: Spring 2022

Harwood Road 12-Inch Water Line Project from Hurst City Limits to Bedfordshire

Description: This is the tenth project utilizing the State Water Implementation Fund for Texas (SWIFT) funding. This project includes the installation of approximately 12,400 linear feet of PVC water pipe, 604 linear feet of iron water pipe, 24" steel casing, and related appurtenances (fire hydrants, valves, meter boxes, and service lines). The project has been prioritized to replace the water lines for Generations Park, to ensure adequate water supply to support the new infrastructure. 

A&M Construction and Utilities, Inc. submitted the lowest qualified bid of the twelve bids received on July 30, 2020. The construction work began on Harwood Road at Bedfordshire on January 12. The project will progress from the east at Bedfordshire toward the Hurst city limits to avoid construction at Generations Park.

After the completion of the waterline project, the City will follow up with pavement improvements on Harwood Road from the Hurst city limits to Bedfordshire.

Project Cost: $2,217,876

Funding Source(s): 2015 Certificates of Obligation Bonds

Anticipated Completion: Spring 2022

West Pipeline Road Water and Sanitary Sewer Replacement from Arwine Cemetery Road to Raider Dr.

Description: This is the twelfth project utilizing the State Water Implementation Fund for Texas (SWIFT) funding. This project includes the installation of approximately 7,400 linear feet of 8-inch water pipe and over 5,500 linear feet of sanitary sewer pipe ranging in size from 6-inches to 15-inches, plus related appurtenances (gate valves, meter boxes, manholes, and pavement replacement).  

A&M Construction Inc. submitted the lowest responsive bid of the eight bids received on September 16, 2021. 

Project Cost: $3,076,712

Funding Source(s): 2015 Certificates of Obligation Bonds, 2012 Certificates of Obligation Bonds, Utility Repair Fund