Construction Projects

Last Updated: February 9, 2024

Gregory and Bedford Court Additions Street and Utility Improvements Project

The project includes street improvements and the replacement of deteriorated sanitary sewer prior to the reconstruction of several streets in the Gregory and Bedford Court Addition. Streets that will be receiving pavement improvements include McCurry Avenue, Prestwick Street, Warwick Street, Windsor Court, Warwick Court, and Gettysburg Place. Sanitary sewer improvements will be along Prestwick Street, Warwick Street, Windsor Court, and Warwick Court. The water lines in the neighborhood were previously replaced by the City under the State Water Implementation Fund for Texas (SWIFT) program.

  • Project Status: Construction Pending
  • Design Cost: $251,657.60
  • Design Consultant: TranSystems
  • Construction Cost: $1,037,688
  • Contractor: GRod Construction
  • Anticipated Construction Start Date: Winter 2023/Spring 2024
  • Anticipated Completion: FY 2025
  • Funding Source(s): 4B,  Utility Repair Fund 505


Cummings Elevated Storage Tank Project

The project includes repair, replacement, and rehabilitation of existing components and internal and external painting of the tank. The following components are included in the project: the addition of a fall protection system, a new 30-inch access hatch, and a new water access ladder. Also included are a 30-inch motor actuated valve inside a new vault to facilitate future work and maintenance of the tank, a submersible mixer to aid in water quality, an online chlorine analyzer to monitor disinfectant residuals and upgrades to the SCADA and electrical systems.

  • Project Status: Under construction
  • Design Cost: $152,417
  • Design Consultant: Garver USA
  • Construction Cost: $2,028,625
  • Contractor: O & J Coatings, Inc.
  • Construction Start Date: Winter 2022
  • Anticipated Completion: Summer 2023
  • Funding Source(s): Utility Repair Fund 505 & 2015 CO SWIFT


West Pipeline Road Utility Replacement Project

The project includes over 7,400 linear feet of water pipe replacement and over 5,500 linear feet of sanitary sewer pipe ranging in size from 6-inches to 15-inches, plus related appurtenances (gate valves, meter boxes, manholes, and pavement replacement) along Pipeline Road from Arwine Cemetery Road to Raider Drive. The City of Bedford owns and maintains various water and sanitary sewer lines under Pipeline Road roadway and within the parkways that serve Bedford residents. These utilities need to be replaced before the reconstruction of West Pipeline Road by the City of Euless.

The design for the project began in April 2020. The construction project was previously awarded in 2020, due to unforeseen circumstances the project was delayed and was re-bid. The construction project was awarded in June 2023 to Canary Construction.  

Construction will begin in summer 2023 with completion in summer 2024. The City of Euless roadway reconstruction project will begin in fall 2023 and will closely follow the completion of the utility project.

  • Project Status: Under construction
  • Design Cost: $251,657.60
  • Design Consultant: Halff Associates, Inc.
  • Construction Cost: $5,121,185
  • Contractor: Canary Construction
  • Construction Start Date: Summer 2023
  • Anticipated Completion: Fiscal Year 2024
  • Funding Source(s): 2015 CO SWIFT, 2010 CO, 2011 CO, 2012 CO, 2012A CO, Utility Repair Fund 505

 

Deuce Drive Water, Sewer, and Street Reconstruction Project 

The project includes the replacement of water, sanitary sewer, and reconstruction of new curbs, gutters, sidewalks, and a concrete driving surface along Deuce Drive, between Tennis Drive and Brown Trail. The project is in an area with large commercial vehicles that carry heavy loads that continue to damage the existing asphalt street.

  • Project Status: Under construction
  • Design Cost: $122,210
  • Design Consultant: Teague Nall & Perkins
  • Design Start Date: Spring 2022
  • Construction Cost: $1,037,668
  • Contractor: GRod Construction
  • Construction Start Date: TBD
  • Anticipated Completion: Fiscal Year 2024
  • Funding Source(s): 2015 CO SWIFT, Utility Repair Fund 505, 2019 CO Bond, SIEDC

 **There will be no access to Deuce Drive, from Tennis Drive to Brown Trail starting February 6, 2024 during Construction**

 

Various Water and Sewer Improvements

The project includes water improvements on Brown Trail, Bedford Road, Oakhurst Drive, Robindale Drive and Court, and sewer improvements on Brown Trail, Chattanooga Drive, Bedford Road, Robindale Drive, and Robindale Court. These locations were selected due to the age and overall poor conditions of the existing water and sewer lines.

  • Project Status: Under construction
  • Design Cost: $402,544
  • Design Consultant: Chiang, Patel & Yerby (CP&Y)
  • Design Start Date: June 2020
  • Construction Cost: $6,410,000
  • Contractor: Excel 4 Construction, LLC
  • Construction Start Date: Fall 2023
  • Anticipated Completion: Fall 2024
  • Funding Source(s): 2017 CO SWIFT, Utility Repair Fund 505, 2019 CO Bond

 

Joiner Acres Project SWIFT 21-09, Bell Manor Units 1-5 SWIFT 21-13 and Forest Ridge Number 2 Addition Water and Sanitary Sewer Improvements

The project includes approximately 16,000 linear feet of 6-inch and 8-inch water pipe and over 3,400 linear feet of 8-inch sanitary sewer pipe. The project combines Joiner Acres Project SWIFT 21-09 and Bell Manor Unit 1-5 and Forest Ridge Number 2 Addition SWIFT 21-13 water and sanitary sewer improvements. The projects have been combined to bid as one project.

On November 6, crews will begin replacing sanity sewer lines on Savannah Way, between Schumac Lane and Natchez Avenue, in the Bell Manor subdivision. Contractors will place notices on doors along Savannah Way before construction begins. 

In next several weeks, crews will also begin work on the following items that are a part of the same project as Savannah Way:

  • Replacing water lines in the area northwest of Pipeline Road to Central Drive. This includes Memphis Drive, Winchester Way, Atlanta Drive, Lexington Place, Charleston Drive and Court, Gettysburg Place, Richmond Drive, Shell Court, and Trinity Court.
  • Replace aging sewer and water infrastructure on Russell Lane/Ravenswood Drive

Please note, crews will notify residents on these affected streets via door hangers before work begins, as well. 

If crews shut down access to a road for an extended period, the contractor will provide a 48-hour notice to homeowners. The contractor will also notify residents before blocking any driveway to allow residents time to move vehicles. Most driveway shutdowns will be for short periods of time to allow crews to pass by with utility work.

Design for the project began in spring 2023. Bidding and awarding was completed in September 2023 with construction scheduled to begin fall 2023. 

  • Project Status: Under construction
  • Design Cost: $37,050
  • Design Consultant: Westwood Professional Services, Inc.
  • Design Start Date: Spring 2023
  • Construction Cost: $4,832,283.25
  • Contractor: SYB Construction Company, Inc.           
  • Construction Start Date: Fall 2023
  • Anticipated Completion: Fall 2024
  • Funding Source(s): 2015 CO SWIFT, Utility Repair Fund 505, and 2019 CO Bond

 

Phyllis Street Utility Replacement and Street Reconstruction

The project includes the reconstruction of the existing curbs, gutters, and driving surface as well as the partial replacement of the aging water and sanitary sewer lines from Brown Trail to Ravenswood Drive. 

Surveying along Phyllis Street will begin the week of September 11, 2023. The design consultant will leave door hangers on affected properties. 

  • Project Status: Under Design
  • Design Cost: $191,000
  • Design Consultant: Teague Nall & Perkins (TNP)
  • Design Start Date: September 2023
  • Construction Cost: TBD
  • Contractor: TBD                 
  • Construction Start Date: FY 2024 
  • Anticipated Completion: FY 2024
  • Funding Source(s): 4B, Tarrant County Grant (CDBG), and Utility Repair Fund 505


Parkwood Drive Improvements between Bedford Road and L. Don Dodson

The project includes the reconstruction of the roadway, including curb and gutter, water, sewer, and drainage improvements between Bedford Road and L. Don Dodson. 

  • Project Status: Under Design
  • Design Cost: $154,170
  • Design Consultant: Huitt-Zollars, Inc.
  • Design Start Date: May 2023
  • Construction Cost: TBD
  • Contractor: TBD                 
  • Construction Start Date: FY 2024 
  • Anticipated Completion: FY 2024
  • Funding Source(s): Economic Development Fund