Posted on: February 15, 2019

SH 121 Construction Update

Highway Construction Update

Anticipated lane closure activity for the week of November 17, 2019

  • SH 121 main lanes (various lanes) northbound and southbound from Bedford Road to Glade Road – Daily closure (9 a.m. to 3 p.m.) 11/18 thru 11/21
  • SH 121 frontage road U-turn (south-to-north) at Harwood Road – Continuous closure 11/17 thru 11/23
  • SH 121 frontage road U-turn (south-to-north and north-to-south) at Cheek-Sparger Road – Continuous closure 11/17 thru 11/23
  • Cheek-Sparger (inside lane) eastbound and westbound under SH 121 - Daily closure (7 a.m. to 5 p.m.) 11/18 thru 11/21
  • Cummings Drive eastbound and westbound under SH 121 – Continuous closure 11/17 thru 11/23 (Detour Harwood to south and Cheek-Sparger to north)
    • ***For safety concerns, pedestrians are prohibited from crossing SH 121 at Cummings Drive during this closure***
  • FM 157 (Industrial Blvd) exit ramp from SH 121 southbound - Continuous closure 11/17 thru 11/23 (Detour to Cheek-Sparger)

Various daily lane closures throughout the project limits are possible from 9:00 a.m. to 3:00 p.m. All closures are subject to weather and schedule changes.

SH121Mobility is a TXDOT project. For more information, please contact Stephen Ranft, mobility coordinator for the SH121 project, at 817-462-0520 and SH121mobility@gmail.com. Visit the TXDOT PROJECT TRACKER at www.txdot.gov/inside-txdot/projects/project-tracker.html

FM 157 Detour Nov 2019 Map

Facebook Twitter Email

Other News in City Spotlights

Bedford Connection Cover with Leaves and Rake

Bedford Connection Fall/Winter 2019

Posted on: August 1, 2019
Phase Next Info & Updates