Anticipated lane closure activity for the week of November 3, 2019
- SH 121 main lanes (various lanes) northbound and southbound from Bedford Road to Glade Road – Daily closure (9 a.m. to 3 p.m.) 11/14
- SH 121 main lanes (inside lane only) northbound and southbound from Bedford Road to Glade Road – Nightly closure (7 p.m. to 6 a.m.) 11/14
- SH 121 frontage road U-turn (south-to-north) at Harwood Road – Continuous closure 11/10 thru 11/16
- SH 121 frontage road U-turn (south-to-north and north-to-south) at Cheek-Sparger Road – Continuous closure 11/10 thru 11/16
- Cheek-Sparger (inside lane only) eastbound and westbound under SH 121 – Daily closure (7 a.m. to 5 p.m.) 11/11 and 11/12
- Cummings Drive eastbound and westbound under SH 121 – Continuous closure 11/10 thru 11/16 (Detour Harwood to south and Cheek-Sparger to the north)
- ***For safety concerns, pedestrians are prohibited from crossing SH 121 at Cummings Drive during this closure***
- FM 157 (Industrial Blvd) exit ramp from SH 121 southbound - Continuous closure 11/11 thru 11/16 (Detour to Cheek-Sparger) (exhibit attached)
Various daily lane closures throughout the project limits are possible from 9:00 a.m. to 3:00 p.m. All closures are subject to weather and schedule changes.
SH121Mobility is a TXDOT project. For more information, please contact Stephen Ranft, mobility coordinator for the SH121 project, at 817-462-0520 and SH121mobility@gmail.com. Visit the TXDOT PROJECT TRACKER at www.txdot.gov/inside-txdot/projects/project-tracker.html